ALTIUS delivers 3x offshore monopile sections to La Seyne-sur-mer, France

 

Three (3x) offshore monopile sections, weighing from 77 to 121 tons maximum, were recently shipped by ALTIUS Project Division Bilbao branch  in January 2016 from the manufacturing plant in Bilbao (Spain) to the destination port of La Seyne-sur-mer, in France.

All the sections were shipped onto the coaster gearless vessel "M/V Barbarossa" stowed on the lower hold. Loading & discharge operations were executed by shore mobile cranes.

 

20160108_152251

20160108_181501

20160108_121246

 

 

ALTIUS delivers 3x offshore sections of a monopile in the port of La Seyne-sur-mer, France

 

Weighing between 77 and 121 tons maximum, they were recently shipped our ALTIUS branch in Bilbao as project cargo, in January 2016, from the production facilities in Bilbao (Spain) to the port of destination in La Seyne-sur-mer, France.

All sections were loaded on board the coastal vessel "M/V Barbarossa" and stowed in the hold, with loading and unloading operations carried out by mobile cranes.

 

 

20160108_181501

20160108_121246

20160108_152251

New achievement of ALTIUS in Peru for ILO NODO SUR PROJECT

ALTIUS Project Division performed last December 2015 a successful land transportation in Peru of 2x sets of Gas Turbines (200 tons gross weight / each) and 2x sets of Generators (256 tons gross weight / each).

Above mentioned heavy-lift units and also the rest of the conventional break-bulk cargo were shipped from Houston Port (USA) to Ilo Port (Peru) onboard the heavy-lifter vessel MV BBC Oregon. Adverse weather conditions were faced at the destination peruan port due to swell influence, but nonetheless, discharging operations were conducted safely and according to the transport schedule.

Gas Turbines units were received ashore and then hauled to project site using a 2×14-axlelines "side by side" conventional modular trailer, and the Generators were transported and delivered to site onto a 2×16-axlelines "side by side" trailer, executing consecutive trips, respectively.

The haulage of each heavy unit, from Ilo Port up to the project site location situated in "Central Termoeléctrica de ILO", is approximately 25 km. and each land-transportation was executed in 5 hours.

IMG-20151012-WA0002

IMG_2859

IMG_2858

 

New ALTIUS achievement in Peru for the ILO transport project NODO SUR

In December 2015, the ALTIUS project division successfully completed the inland transport of 2x sets of Gas Turbines (200 tons gross unit weight) and 2x sets of Generators (256 tons unit weight).

The above-mentioned heavy equipment and also other general cargo were loaded from the port of Houston (USA) to the port of Ilo (Peru) onboard the heavy-lifter MV BBC Oregon. Adverse weather conditions were encountered at the Peruvian port of destination due to the influence of swell and rough seas, but despite this fact, the unloading operations were carried out safely and according to the transport schedule.

The Gas Turbines were received ashore from the vessel and then transported to the project site using a conventional modular trailer with a 2×14-axle-line "parallel platform" configuration, and the Generators were transported and delivered to site by trailer with a 2×16-axle-line "parallel platform" configuration, making consecutive trips, respectively.

The land transport of each piece of heavy equipment from the port of Ilo to the project site at the "Central Termoeléctrica de ILO" is approximately 25 km away, with each transport taking 5 hours.