Unloading of Sun Master Vessel Carrying Cargo for Potosi's Cement Plant
Potosi's Cement Plant works continue. Unloading of the third breakbulk shipment was recently carried out at Arica Port in Chile. An ALTIUS engineer was present to oversee operations, to guarantee they were carried out properly, and to be able to inform client in full.
Cargo was labeled according to the project's code and stowed at the port in order to estimate a proper delivery schedule to the Cement Plant. Land transportation from Arica to Potosi (Bolivia) is set to begin the following week, the number of trucks involved being stipulated by the client (according to work site limitations).