Potosi Cement Plant Project
Altius continues to make progress with the logistics project for the cement plant in Potosí (Bolivia), a project for which they have been contracted by Sacyr Industrial. The project began in January 2018 with the first container shipments.
Apart from the containerized cargo, Altius is also in charge of the coordination of the onshore part of the project cargo (8 shipments unloaded and delivered, and one shipment in sea transit), which includes assistance for unloading in Arica (Chile) and transport to the construction site (where a person must travel to the site to receive the documentation and direct the drivers for the correct unloading). So far, the progress of the project can be summarised as follows:
- Breakbulk cargo: 9 shipments/ 360 packages/ 3.650 T / 19.000 CBM
- FCL Cargo: 322 containers (619 TEUs)