Unloading of Sun Master ship with cargo for Potosi Cement Plant

By 17 de May de 2018February 10th, 2024News, Projects

Work continues on the Potosi Cement Plant. The third shipment of breakbulk cargo was recently unloaded at the port of Arica (Chile). An ALTIUS engineer has been present during the same to guarantee a correct operation and to be able to inform the customer properly.

yellow crane

All cargo was labeled according to project code and stowed at the port in order to estimate a delivery sequence to the plant. Ground transportation from Arica to Potosí (Bolivia) will begin the following week, in accordance with the number of trucks stipulated by the client (according to site limitations).